Cedar Falls Weekly Construction Updates: September 20, 2021

Update

City of Cedar Falls issued the following announcement on September 20.

View the latest Cedar Falls street construction updates for the week of September 20, 2021:

Downtown Streetscape and Reconstruction Project- On East 4th Street, the contractor has poured the mainline pave and will continue with the parking stall pours after the concrete work on the west side of the 500 block of the parkade has been completed. The contractor has begun placing the concrete amenity pads along the parkade, and will be followed by the bricklaying contractor as they complete the west side of the 500 block.

To learn more about the Streetscape and sign up for regular email updates, visit cedarfalls.com/downtown.

West 1st Street/HWY 57 Expansion- For the week of September 20, crews will be working on installing sidewalk and trail on the north side of West 1st Street/HWY 57, placement of sod, and also placement of new signage. As crews work to finalize the project, lane closures should be expected for work behind the back of the curb and also for painting operations. Near the Hudson Road intersection, the current head-to-head traffic will continue as crews wrap up the northern side of the intersection. This will continue to result in restricted turning movements at the Hudson Road intersection. Trailered vehicles should choose alternative routes to avoid turning at the intersection. 

To learn more about the West 1st Street/HWY 57 Expansion and sign up for regular email updates, visit cedarfalls.com/1455/Hwy-57-W-1st-Street-Expansion-Project.

2021 Street Construction Project

Learn more about the roads involved in the 2021 Street Construction Project and sign up for regular email updates at bit.ly/cf21StConstruction.

Brandilynn Boulevard (Stage 3) will be ready for concrete paving this week.

McClain Drive (Stage 2) has now paved the roadway and will continue working on the intersection pours and driveway and sidewalk replacement.                                               

Tremont Street has been paved and will be followed up with the seeding in the following weeks.                      

Kaspend Place spot repairs are underway. Driveways will be poured back soon and then followed with an asphalt overlay on the street.               

Union Road Recreational Trail          

During the week of September 20,  paving operations will continue working north. Traffic will be maintained on Union Road throughout the project. Paving is to continue in the following weeks and the contractor plans on working on grading and forming in the week to follow.

Cedar Heights Drive Reconstruction (Cedar Heights Drive & Greenhill Road)

For the week of September 20 crews will continue to install storm sewer on the north half of the Greenhill Road and Cedar Heights Drive intersection. After the storm sewer is complete, crews will start preparing the roadway for paving in the following week. The current traffic pattern will continue with East and Westbound traffic on Greenhill Road maintained throughout construction. Cedar Heights Drive traffic is currently detoured around the intersection closure by posted detour signage on the following roadways: Viking Road, Prairie Parkway, Greenhill Road, and University Avenue. Chadwick Drive will be open for business and residential access to Greenhill Road throughout the remainder of the project.

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS